<div style="text-align: justify;"><span style="color:#00008B">These thirteen boats were one of three contracts awarded to the Electric Boat Company of New York City (later Groton, CT.). Electric Boat did not have a construction yard yet at its NELSECO engine plant in Groton, so these boats were sub-contracted to the Fore River Shipbuilding Company of Quincy, MA. By the time of the start of construction, the yard had been sold to Bethlehem Steel, and was officially known as Bethlehem Quincy. These boats were all single hull submarines, with all ballast tanks inside the pressure hull. | <div style="text-align: justify;"><span style="color:#00008B">These thirteen boats were one of three contracts awarded to the Electric Boat Company of New York City (later Groton, CT.). Electric Boat did not have a construction yard yet at its NELSECO engine plant in Groton, so these boats were sub-contracted to the [http://shipbuildinghistory.com/shipyards/large/bethquincy.htm '''Fore River Shipbuilding Company of Quincy, MA.'''] By the time of the start of construction, the yard had been sold to Bethlehem Steel, and was officially known as Bethlehem Quincy. These boats were all single hull submarines, with all ballast tanks inside the pressure hull. | ||
S-1 was the first boat of the group completed, and while she was running trials she encountered severe torsional vibrations in her NELSECO 8-EB-15 diesel engines, [https://pigboats. | S-1 was the first boat of the group completed, and while she was running trials she encountered severe torsional vibrations in her NELSECO 8-EB-15 diesel engines, [https://pigboats.com/images/b/b9/The_Devil_in_the_Details_TSR_version.pdf '''bad enough that the engines were completely wrecked''']. A defect was found in the design of the crankshaft. The process of getting this problem fixed was a long and drawn-out affair, greatly delaying the introduction of these boats to the fleet. However, once fixed these boats provided great service to the fleet, with many of them serving through WWII. | ||
For more information, please see the [https://pigboats. | For more information, please see the [https://pigboats.com/images/d/d4/A_VISUAL_GUIDE_TO_THE_S-CLASS_SUBMARINES_PART_3_Third_edition.pdf '''article at this link.''']</span></div> | ||
[[File:Red bar sub.jpg]] | [[File:Red bar sub.jpg]] | ||
=== <big>S-1 (SS-105)</big> === | === <big>S-1 (SS-105)</big> === | ||
[[File:Uss s1 launch.jpg|left|500px|USN photo from the Rick Larson Collection, now in the private collection of Ric Hedman.]] | [[File:Uss s1 launch.jpg|left|500px|USN photo from the Rick Larson Collection, now in the private collection of Ric Hedman.]] | ||
Line 37: | Line 37: | ||
=== <big>S-20 (SS-125)</big> === | === <big>S-20 (SS-125)</big> === | ||
[[File:S-20 trials.jpg|left|500px|USN photo # NH 108000 via NHHC]] | [[File:S-20 trials.jpg|left|500px|USN photo # NH 108000 via NHHC]] | ||
<div style="text-align: justify;"><span style="color:#00008B">S-20 on builder's trials off Provincetown, MA. October 7, 1920. Engine troubles would keep her from being commissioned for nearly two more years.</span> | <div style="text-align: justify;"><span style="color:#00008B">S-20 on builder's trials off Provincetown, MA. October 7, 1920. This is her as-built configuration, with the vertical "chisel" bow with hawsepipe, slab-sided bow plane pivot fairings, narrow and flat forward deck, and original style aft superstructure skeg. She is running at 11.6 knots on the measured mile range, which is below her rated maximum of 13 knots. [https://pigboats.com/images/b/b9/The_Devil_in_the_Details_TSR_version.pdf '''Engine troubles'''] would keep her from being commissioned for nearly two more years.</span> | ||
[[S-20|See more S-20 photos]] | [[S-20|See more S-20 photos]] |
Latest revision as of 08:33, 14 October 2024
Design and Construction Notes
S-1 was the first boat of the group completed, and while she was running trials she encountered severe torsional vibrations in her NELSECO 8-EB-15 diesel engines, bad enough that the engines were completely wrecked. A defect was found in the design of the crankshaft. The process of getting this problem fixed was a long and drawn-out affair, greatly delaying the introduction of these boats to the fleet. However, once fixed these boats provided great service to the fleet, with many of them serving through WWII.
For more information, please see the article at this link.S-1 (SS-105)
S-18 (SS-123)
S-19 (SS-124)
S-20 (SS-125)
S-21 (SS-126)
S-22 (SS-127)
S-23 (SS-128)
S-24 (SS-129)
S-25 (SS-130)
S-26 (SS-131)*
S-27 (SS-132)*
The S-27 served the Navy well until 13 June 1942. On that date she was on patrol in the Aleutian Island chain off Alaska. In the black of night in poor visibility she ran aground on the rocks off the southern tip of the island of Amchitka. She was stuck fast and mounting seas started to batter the boat to pieces. Her entire crew escaped and spent the next 12 days marooned on the island until they were rescued by four PBY patrol planes. Unfortunately, the S-27 was a total loss. Her wreck was quickly broken up and destroyed by the sea action.
S-28 (SS-133)*