168 launch

From PigBoats.COM
Revision as of 17:11, 25 June 2023 by Pbcjohnston (talk | contribs) (Reformatting)


Mare Island Navy Yard, Building Ways #2, Vallejo, California, August 27, 1927, the construction of the V-6 is about to begin. Navy and yard officials and workman line up for the official keel laying photograph. The banner proclaims: "When Better Submarines Are Built Mare Island Will Build Them"

From left to right: Front row; LT J. W. (Duke) Paige, C.C., Ship Supt; CDR E. L. Patch, C.C., Asst. Inside Supervisor, New Work Hull (In general charge of Keel Laying Arrangements); CDR F. J. Wille, Outside Supt.; CAPT C. S. McDowell, Inside Supt.; LCDR W. C. Wade, Asst. Shop Supt.; RADM J. H. Dayton, Commandant Mare Island Navy Yard; CDR E. D. (Bill) Almy, Shop Supt.; J. T. Moroney, Master Shipfitter.

Back Row: Fred Coppo, Rivet Heater; A. P. Schneidewind, Riveter; J. F. Nichelini, Holder-on (all members of regular riveting gang); Honorary Riveting Group: A. L. Luck, Leadingman Shipwirght "Riveter"; W. L. Blackmore, Leadingman Pipefitter "Rivet Passer"; J. E. Moon, Leadingman Machinist "Rivet Heater"; Charles Deaver, Quarterman Riveter "Rivet Heater"; Tom Schofield, Master Rigger & Laborer "Holder-on"; B. A. (Bert) Barr. Quarterman Shipfitter "Riveter"; F. W. Savage, Quarterman Electrician "Rivet Tester"; J. R. Greig, Asst. Shop Supt. "Rivet Tester.

The primary construction method was obviously riveting. But at this time there were experiments underway at Navy yards to incorporate welding. Although not shown in this photo, some non-critical areas such as pipe brackets, superstructure supports, and interior deck joinery were welded.

U.S. Navy photo courtesy Darryl Baker

The construction of the V-6 has begun. In a keel laying ceremony, officials and workmen ceremonially drive the first rivet in the hull. The first of what will be millions that this vessel will take before she is finished. The workmen and officials all wear an arm band with "V-6" printed on it.

U.S. Navy photo courtesy Darryl Baker

The rivet team seen in close up. To the left is the forge where rivets are heated. Hot rivets are taken from the forge by one man and passed to a "tosser" and the rivet is caught and shoved through the pre-drilled hole and held in place by a "bucker" who holds a tool with the shape of the rivet head in it on the rivet's head. The two men on the right are using large hammers to "peen" the other end of the rivet up tight to the hull plates. When the rivet cools it will shrink tight.

U.S. Navy photo courtesy Darryl Baker

Almost 13 months after laying the keel the V-6 has pretty much filled the scaffolding at the Mare Island Navy Yard. The date is September 8, 1928. It will still be another year and a half before she touches water. You can see the two massive mounts for the 6 inch/53 caliber guns that will sit on her decks. V-6 and her sisters were all full double hull submarines. The outer ship-shaped hull was wrapped around the inner cigar-shaped pressure hull, with the void spaces between containing the fuel and ballast tanks.

U.S. Navy photo courtesy Darryl Baker

View of V-6 from the port side while on the builder's ways. Construction has moved further along, with the superstructure sides being essentially complete, and work is underway on the gun decks.

From an original glass plate negative in the private collection of Ric Hedman

The next step in construction of V-6. Work is progressing on the conning tower fairwater and bridge area.

Photo courtesy of Darryl Baker

Ric Hedman Photos

Darryl Baker Photos


Ric Hedman Photos